South Africa, Gabon, and Ghana Disrupted Simultaneously: Is the Manganese Ore Supply Chain Becoming Unbalanced?
The global manganese ore market is currently in a delicate state: prices have not collapsed, inventories have not collapsed, but every major link in the supply chain is under strain at the same time. The three most important manganese ore-producing countries in the world—South Africa, Gabon, and Ghana—have experienced disruptions of different natures within almost the same time window. This is not a coincidence, but resonance.
I. The Three-Country Disruption: A Panoramic View
| Country | Global Manganese Ore Position | Disruption Type | Nature of Impact | Timeframe |
|---|---|---|---|---|
| South Africa | World's largest producer; reserves account for approximately 70–80% of global total | Transnet railway heavy load, port constraints, tax reform | Long-term structural; recent improvement signals are mixed | Persistent for years; reform acceleration entering 2026 |
| Gabon | World's second-largest; Moanda is the world's largest manganese mine | Rainy season transport interruptions, coup-related political instability, resource nationalism | Seasonal + policy dual uncertainty | Situation ongoing; 2029 ban approaching |
| Ghana | Sixth-largest globally; Nsuta mine is West Africa's major manganese ore repository | Industry-wide audit + policy uncertainty | Compliance uncertainty leading to investment wait-and-see | Audit Nov 2025–Jun 2026, ongoing |
Data sources: CNBC Africa (2026), Minerals Council SA, Mining Technology (Oct 2025), Eramet official (Jun 2025).
II. South Africa: Structural Cracks Behind Record Exports
2.1 Record Exports—Why This Is Not Good News
South Africa's 2025 manganese ore exports reached 26.2 million tonnes, an all-time high (the previous peak was 22.3 million tonnes in 2024). But behind this figure lies a cautionary tale: the manganese ore business profit of South Africa's major manganese ore producer African Rainbow Minerals (ARM) fell 76% year-on-year, due to a 22% slump in ore prices. The extra tonnes happened to meet the bottom of the price cycle.
This seemingly independent supply increase is closely related to the systemic decline of the Transnet rail and port transport network. To understand how deep the causes run, look at South Africa's freight rail volumes, which have fallen from a 2017 peak of 226.3 million tonnes to 149.5 million tonnes in 2022—a 34% decline and a historic low in recent years. The Port Elizabeth (Ngqura) corridor on which manganese ore depends faces structural constraints such as hillside collapses, equipment aging, and electricity theft every year.
2.2 Clear Reform Signals, But Uncertainty Remains
South Africa is advancing a major round of reforms:
- Railway liberalization reform. In August 2025, the Department of Transport shortlisted 9 qualified private train operators (selected from 25 applicants), authorizing them to transport freight on 41 routes. Network access agreements with terms of 1–5 years are being signed. The manganese ore corridor is listed as a priority.
- New port investment portfolio. Transnet announced it will launch tenders for the Ngqura manganese ore terminal project around April 2026, planning to add 16 million tonnes of annual handling capacity. Maryke Burger, CEO of ARM's Mining Division, has said that if the tender package includes rail operating rights, the company will consider participating.
But the core contradiction is difficult to eliminate in the short term. Transnet's financial condition is beset by long-standing problems—the government has provided tens of billions of rand in backstop guarantees just to keep it afloat. Maintenance costs are a heavy burden, and some cost overruns are passed on to the mining sector, ultimately borne by downstream buyers.
South Africa manganese ore supply chain data snapshot (sources: CNBC Africa, ARM annual report, Engineering News):
- 2025 manganese ore exports: 26.2 million tonnes (all-time high); 2024: 22.3 million tonnes
- ARM manganese business profit: down 76% year-on-year in the period; ore prices down 22%
- Transnet freight rail volumes: down 34% from the 2017 peak, hitting a historic low in recent years by 2022
- Reform progress: 9 new private train operators approved in August 2025; Ngqura terminal project tender in April 2026
III. Gabon: Three Layers of Pressure—Rainy Season, Political Situation, and the 2029 Ban
3.1 Rainy Season Transport Interruptions: The Nerve of a Recurring Disruption
All of Gabon's manganese ore depends on the SETRAG Trans-Gabon railway (total length 648 km) to reach the port for export. Gabon has an equatorial tropical climate, with the rainy season mainly divided into two phases: the long rainy season from February to April and the short rainy season from October to November. During each rainy season, landslides, roadbed subsidence, and derailments caused by permanent wetlands are routine. SETRAG data shows that the line records 6–7 derailments per year, but the actual figure is far higher. Cumulative annual downtime often reaches weeks or even months.
3.2 Policy Uncertainty: Confused Discourse on Two Levels
The 2023 coup ended the Bongo family's 56-year rule. The new government has created confused discourse on two levels: on the one hand, it declares that corporate concession agreements will be "re-examined"; on the other hand, in June 2025 it announced a ban on the export of raw manganese ore effective January 1, 2029. Eramet has received unclear signals: it is being asked to build manganese smelting facilities, yet Gabon itself does not have a stable electricity supply.
In February 2026, Gabon's Minister of Mines publicly stated that energy shortages are not a reasonable justification for delaying the 2029 deadline, rejecting Eramet's arguments. In the same period, Eramet also faced internal management turmoil following the dismissal of its CEO. From a practical standpoint, the uncertainty in this situation will last at least three years.
Gabon manganese ore supply chain data snapshot (sources: Eramet official announcements, Mining Weekly, USGS):
- 2024 Gabon manganese ore production: approximately 4.6 million tonnes; world's second-largest manganese ore-producing country (South Africa is first)
- Comilog is regarded as the world's largest single mine operator of high-grade manganese ore
- SETRAG railway supply stability: historically, cumulative rainy-season downtime averaged weeks to months per year
- The June 2025 announcement of the 2029 raw ore export ban immediately caused Eramet's share price to plunge 5.5% in a single day
IV. Ghana: Policy Uncertainty Under the Largest Mining Audit in a Decade
4.1 Audit Background: Tightening After a Decade-Long Gap
Ghana is a major exporter of gold and manganese ore in West Africa. Its main manganese ore-producing area, the Nsuta mine (operated by Consolidated Minerals), is operated by Consolidated Minerals Africa (90% privately held by Australian interests), with the Ghanaian government holding a 10% stake.
On October 31, 2025, Ghana's Minerals Commission announced the largest-ever mining audit in the country: from November 2025 to June 2026, a comprehensive physical and financial audit of all operating mining companies nationwide. This is the first mining inspection of this scale in Ghana in nearly a decade (the previous one was in 2015).
4.2 Main Audit Content and Investigation Details
The Minerals Commission of Ghana has stated the audit's objectives: to examine production data, mining tax payments, environmental compliance, royalty payments, and possible mineral smuggling and irregular buying and selling. Each mining company is required to submit, by October 31, 2025: 10-year production logs, 3-year financial records, all mining licenses, and inventory and shipment lists. The corresponding on-site audit report for each company must be submitted within 30 days of the site entry date.
The audit itself does not equal a production halt. But the compliance uncertainty it creates is the market's real focus. For investors who have previously engaged with the Ghana situation: what they fear most is not an audit penalty being issued, but being unable to advance any project decisions while waiting for the audit results to come out.
Key information on the Ghana audit (sources: Mining Technology, Mining.com, Kitco, Oct 31, 2025):
- Audit period: November 1, 2025 to June 2026 (phased rollout)
- Starting sites: Gold Fields' Damang mine and Perseus (gold mining company)
- Final site: Xtra-Gold's Kibi block (end of June 2026)
- Key threshold for Ghana: first mining-specific audit involving external investigators since 2015
- Mining's contribution to Ghana's GDP: mining operations contributed 2024 output of 17.77 billion Ghanaian cedis (US$1.68 billion)
V. Multi-Point Resonance: Why This Time Is Different
5.1 Intrinsic Differences Among the Three Disruptions
Viewed individually, the disruptions in the three countries are entirely different in nature:
South Africa: Rising volume, falling price. Export volumes hit records, but with constrained refining capacity and an undivided railway situation, profitability is difficult to achieve. This is a market that has gained volume but lost price.