Southern Manganese Bets on Njolé: Gabon’s Mining Ban Countdown Begins – A Memorandum of Investment That Is Actually a Battle for Mining Rights Under the 2029 Ban

Southern Manganese Bets on Njolé,
Gabon’s Mining Ban Enters Countdown Phase

What Appears to Be an Investment Memorandum
Is in Fact a Defense of Mining Rights Under the 2029 Ban

Core Summary ● On November 6, Emmanuel Eyeghe Nze, Gabon’s Minister of Commerce, Industry and Transformation, signed a memorandum of understanding (MOU), not a binding development agreement, with Zhang He, Chairman of the Board of Directors of South Manganese Investment, in Beijing. The investment amount is 116.7 billion CFA francs, approximately €178 million. ● The project is located in the M’Bembélé mining area north of Njolé. Phase I has an annual capacity of 180,000 tons, with plans to increase to 1.08 million tons/year around 2030; however, it remains unclear whether this capacity refers to metallurgical products or ore throughput, as reports vary. ● South Manganese has been mining locally through its subsidiary CICMHZ (51% owned) for nearly two decades. The mining rights expire in December 2027. In the first half of 2026, sales of Gabonese ore amounted to approximately 709,100 tons, a year-on-year decrease of 6% (estimated). ● Gabon announced a ban on manganese ore exports effective January 1, 2029, a policy declared in late May 2025. Compared to the 2025 production volume of approximately 9.1 million tons, the local processing plans announced by Eramet and South Manganese cover only a small fraction. ● Mineral Cube Assessment: This MOU is primarily South Manganese’s “compliance answer” submitted to renew mining rights and align with the ban, having limited short-term impact on global manganese supply. What truly determines Gabon’s manganese supply is how the 2029 ban is ultimately implemented.

01 Trigger

The Weight of a Single Memorandum

On November 6, the Government of Gabon and South Manganese Investment Limited (South Manganese, HKSE: 1091, formerly CITIC Daming) signed a document in Beijing proposing the construction of a metallurgical complex integrating mining, beneficiation, and smelting in the M’Bembélé mining area north of Njolé, along with supporting energy and logistics facilities. The signatory for Gabon was Emmanuel Eyeghe Nze, Minister of Commerce, Industry and Transformation and Government Spokesperson; for South Manganese, it was Board Chairman Zhang He. South Manganese specializes in manganese, with business operations covering domestic and international manganese ore mining, electrolytic metal manganese and silicomanganese alloy smelting, as well as battery materials such as electrolytic manganese dioxide and manganese sulfate.

While some sources refer to this document as a “development agreement,” the original text from multiple Gabonese media outlets describes it as a mémorandum d’entente, i.e., a Memorandum of Understanding. An MOU expresses intent to cooperate but does not constitute a final investment decision. Local Gabonese media also cautioned that commitments within the MOU must be translated into actual industrial projects; no start date, financing arrangements, or binding clauses have been published to date.

Other key figures can be largely verified: the investment amount is 116.7 billion CFA francs, which converts to approximately €178 million based on the fixed exchange rate between CFA francs and euros (estimated); phase I capacity is 180,000 tons/year, scaling up to 1.08 million tons/year. Gabon was the world’s second-largest manganese producer in 2024, with the U.S. Geological Survey estimating its output accounts for roughly one-quarter of global production; 2025 production was approximately 9.1 million tons, a year-on-year decline of 2.5%.

Key PointSource ClaimVerification Status
Document NatureDevelopment Agreement / Preliminary AgreementMemorandum of Understanding, non-binding
Signing LocationChinaBeijing
Investment Amount116.7 billion CFA francsConsistent, approx. €178 million
Capacity180k tons → 1.08M tonsConsistent, product definition unclear
TimelineProduction reach by 2030Million-ton scale achieved around 2030
GDP ContributionManganese accounts for ~6%Overall mining sector accounts for ~6%

Note: Gabon’s statistical reporting of manganese production refers to raw ore tonnage, not metallic manganese content.

02 Background

Two Decades at Njolé

South Manganese is no stranger to Gabon. Its Gabonese subsidiary, CICMHZ, was established in 2005 to develop manganese deposits around Njolé. According to South Manganese’s 2025 Annual Report, the company holds a 51% equity stake in CICMHZ. The M’Bembélé mining license was issued in December 2007, renewed twice—in 2017 and December 2022—with the most recent renewal covering 41.17 square kilometers for a five-year term, expiring in December 2027. In February 2021, CICMHZ also signed a new mining agreement with the Gabonese government, paving the way for state participation.

In terms of resources, the Bembélé mining area contains 70.24 million tons of mineral resources, including indicated reserves of 9.81 million tons. Operationally, in the first half of 2026, CICMHZ sold 709,106 tons of Gabonese ore, compared to 757,191 tons in the same period last year—a volume decrease of approximately 6% (estimated). However, due to higher selling prices, revenue increased rather than declined.

Njolé’s location is also noteworthy. It is situated along the Ogooué River in central Gabon, positioned between the eastern mining areas and Atlantic coastal ports, near the existing Trans-Gabon Railway corridor. Another Chinese enterprise, Guangxi Yuanhai Mining Group, participated in the Njolé inland port project, which held an inauguration ceremony in June 2024, though subsequent progress encountered obstacles, and support from Chinese financial institutions is still being sought.

ProjectData
Operating EntityCICMHZ, established in 2005
South Manganese Stake51% (per 2025 Annual Report)
Mining LicenseIssued December 2007, expires December 2027
License Area41.17 square kilometers
Mineral Resources70.24 million tons
Indicated Reserves9.81 million tons
H1 2026 Sales Volume709,106 tons, approx. -6% YoY (estimated)

03 Analysis

What Does 1.08 Million Tons Refer To?

The biggest question surrounding this memorandum concerns the definition of capacity. One Gabonese media outlet described phase I as producing “180,000 tons of metallurgical products,” while another financial publication explicitly stated that whether the 2030 capacity refers to ore throughput or processed products remains to be clarified. These two interpretations imply vastly different project scales.

Eramet’s data can serve as a reference point. Eramet’s planned coastal manganese alloy plant has an annual alloy production capacity of 265,000 tons, requiring the processing of approximately 530,000 tons of ore—meaning roughly 2 tons of ore are consumed per ton of alloy. By this logic, if the 1.08 million tons figure refers to alloys, it would require approximately 2.16 million tons of ore, which is about 1.5 times CICMHZ’s current annual sales volume (H1 2026: 709,100 tons, annualized to approx. 1.42 million tons) (estimated). If, however, the figure refers to ore throughput, then most of the output may still be concentrate, with significantly less smelting involved.

The investment amount also provides clues. The Moanda Metallurgical Complex, commissioned in 2015, required an investment of approximately $300 million, with combined silicomanganese and metal manganese capacities of about 85,000 tons, plus an additional government investment of approximately $400 million for supporting hydropower infrastructure. South Manganese’s project, with an investment of €178 million against 1.08 million tons of capacity, represents only a fraction of the unit capital expenditure of the previous project. Based solely on this funding level, it is difficult to justify building million-ton-scale alloy smelting capacity. A more reasonable inference is that the 1.08 million tons primarily refers to mining and beneficiation scale, with smelting constituting only a portion of the operation.

Interpretation MethodCorresponding Ore RequirementComparison with Existing Scale
1.08 million tons as alloy productsApproximately 2.16 million tons (estimated)Approximately 1.5 times the annualized sales volume
1.08 million tons as run-of-mine ore inputApproximately 1.08 million tonsLower than the annualized sales volume
Phase I: 180,000 tons as alloysApproximately 360,000 tons (estimated)Approximately 25% of the annualized sales volume

Note: Annualized sales volume is calculated by multiplying the first half of 2026’s figure of 709,106 tons by two, resulting in approximately 1.42 million tons; the ore-to-alloy ratio reference follows Eramet’s coastal alloy plant planning.

Turning to resource security. If calculated based on an annual consumption of 1.08 million tons of ore, the approximate reserves of 9.81 million tons would suffice for approximately nine years of mining (estimated); if calculated on an alloy basis, they would last only about 4.5 years (estimated). The extent to which resources within the 70.24 million ton resource base can be upgraded to reserves directly determines the scale and duration of this project.

04 Deconstruction

The Countdown to the 2029 Ban

Materials indicate that Gabon “plans to prohibit manganese raw ore exports starting in 2029.” This is not new news. In late May 2025, President Brice Clotaire Oligui Nguema ordered during a cabinet meeting that the export of raw manganese ore be formally prohibited effective January 1, 2029, providing a three-year preparation period for mining enterprises and promising the establishment of a public-private partnership investment fund. The ban applies only to unprocessed manganese ore and does not affect the export of processed products such as high-carbon ferromanganese. Following the announcement, Eramet’s share price fell by approximately 4.9% on the same day.

Since then, Gabon’s stance has remained firm. In February 2026, Minister of Mines Sosthène Nguema Nguema stated during the Cape Town Mining Indaba that energy shortages cannot serve as grounds for non-compliance with the 2029 deadline; all manganese mining companies must submit detailed implementation schedules and demonstrate measurable progress. France had previously called for greater flexibility regarding these timelines. Concurrently, Eramet signed a memorandum of understanding (MoU) with the Gabonese government regarding local processing.

DateEvent
Late May 2025Gabon announces prohibition of raw manganese ore exports effective January 1, 2029
June 2025New Gabonese mining company confirms construction of alloy facilities
February 2026Mining Minister states the 2029 deadline is non-negotiable
July 20, 2026Eramet signs MoU with Gabon for local processing
November 6, 2026Southern Manganese signs MoU with Gabon for the Njole Project
December 2027M’Bembélé mining license expires
January 1, 2029Raw manganese ore export ban takes effect

Placed against this timeline, the intent behind Southern Manganese’s MoU becomes clearer: with mining rights expiring at the end of 2027 and the ban taking effect in early 2029, the company must present a local processing plan prior to renewal. For a mining enterprise operating locally for nearly two decades, the MoU serves both as an expression of investment intent and as a document demonstrating compliance to the government.

05 Comparison

How Much Can Local Processing Absorb?

Gabon’s manganese production is dominated absolutely by Comilog, under Eramet. The Moanda mine produced approximately 7.1 million tons in 2025, accounting for roughly 13% of global supply. The Eramet MoU signed in July outlines three scenarios: constructing a pyrolusite plant in the Libreville region with an annual capacity of 10,000 tons, scheduled to commence operations by the end of 2028 at the latest; refurbishing the Moanda metallurgical complex, targeting an annual output of up to 70,000 tons of alloys and processing approximately 150,000 tons of ore, aiming to resume operations before the end of 2029; and building a new coastal factory with an annual capacity of 265,000 tons of manganese alloys, earliest operational date 2031. Combined, these projects could process up to approximately 700,000 tons of ore locally by the end of 2031.

Company / ProjectPlanned CapacityOre Processing VolumeTimeline
Eramet Pyrolusite Plant10,000 tons/yearApproximately 20,000 tonsEnd of 2028
Refurbishment of Moanda Metallurgical ComplexUp to 70,000 tons of alloysApproximately 150,000 tonsEnd of 2029
Eramet Coastal Alloy Plant265,000 tons of alloysApproximately 530,000 tons2031
Southern Manganese Njole Project180,000 tons → 1.08 million tonsBasis unclearAround 2030
New Gabonese Mining CompanyAlloy facilityUndisclosedUndisclosed

The gap is evident when compared to production volumes. Gabon’s manganese production was 9.442 million tons in 2024 and approximately 9.1 million tons in 2025; the 2026 fiscal budget assumes 9.525 million tons, while the 2027 draft budget assumes 10.35 million tons. Eramet’s planned processing capacity of 700,000 tons represents only approximately 7.7% of 2025 production levels (estimated); even if Southern Manganese’s 1.08 million tons are fully counted on an ore basis, local processing capacity digestible by 2031 will still account for less than 20% of Gabon’s production (estimated).

YearGabon Manganese ProductionYoY Change
20249.442 million tons-5.3%
2025Approximately 9.1 million tons-2.5%
2026 (Budget)9.525 million tonsApproximately +4.7% (estimated)
2027 (Draft Budget)10.35 million tons+8.6%

Beyond the capacity gap, there are two hard constraints. First, electricity: manganese alloy smelting is highly energy-intensive, and the Grande Dévoluy region recently implemented rolling blackouts lasting three hours per day. Second, transportation: rail capacity across Gabon has become a bottleneck. In Q3 2025, shipments from the Moanda mine decreased by 13% year-on-year, forcing Comilog to adjust production and shipment volumes according to rail capacity.

06 Assessment

The MoU as a Compliance Response

Kuanglibang’s assessment is that this MoU is primarily a compliance response submitted by Southern Manganese to renew its mining rights and align with the 2029 ban; it will not alter global manganese ore supply and demand in the short term. CICMHZ’s annual sales volume of over one million tons is merely a fraction of Gabon’s production exceeding 9 million tons. The product specifications, funding arrangements, and commencement dates for the project have yet to be finalized. Between the signing of the MoU and actual production, there are at least three hurdles: feasibility studies, investment agreements, and energy infrastructure support.

The market currently lacks no ore. Data from Eramet shows that global manganese ore demand declined by 7% quarter-on-quarter to 4.9 million tons in Q3, while supply also decreased by 7% to 5.1 million tons, leaving the market still in surplus. Chinese port manganese ore inventories rose from 5.7 million tons at the end of June to 6.2 million tons at the end of September, equivalent to approximately 12 weeks of consumption. Comilog’s quotations to China rose in the first half of the year, retreated mid-year, and saw a slight increase in Q4. December shipment 44.5% lumpy ore was quoted at $4.90/tmd, a quarter-on-quarter increase of $0.10, but remains significantly lower than the $5.45/tmd quoted for June shipments.

Shipping ScheduleComilog 44.5% Fines Quote (USD/t, CIF China)
January 20264.70
June 20265.45
July 20265.18
August 20265.10
September 20264.90
November 20264.80
December 20264.90

For China, Gabonese ore is one of the most important high-grade sources. Customs data shows that from January to November 2025, China’s cumulative manganese ore imports reached 29.568 million tons, a year-on-year increase of 10.39%; notably, in July 2025 alone, manganese ore imports from Gabon amounted to 486,200 tons. Gabonese pyrolusite ores are characterized by high grade and low impurities, primarily serving to enhance the charge grade in alloy plant blending. Spot prices at ports in both northern and southern China have consistently remained significantly higher than those for South African semi-carbonate ores.

What truly warrants attention is the supply structure post-2029. If the ban is strictly enforced and local processing capacity can only absorb less than 20% of production, exports of Gabonese high-grade pyrolusite ores face the risk of disruption. A more realistic scenario may involve Gabon granting transitional arrangements based on enterprise progress during implementation, or classifying products after beneficiation and sintering as “processed goods.” These two scenarios would have vastly different impacts on Chinese alloy plants: the former implies an elevation in premiums for high-grade ores, while the latter would largely maintain existing trade flows. The specific details of the ban are far more critical than any memorandum.

07 Outlook

Three Signals to Monitor Implementation

Tracking Point 1: Renewal of Bembélé Mining Rights and Formal Investment Agreement. With the mining license expiring in December 2027, whether the memorandum can be converted into a binding investment agreement prior to this date—clearly defining production capacity metrics and construction timelines—constitutes the first hurdle in assessing the project’s viability.

Tracking Point 2: Detailed Implementation Rules of the Ban. Current public information indicates that the ban targets unprocessed manganese ores, with products such as high-carbon ferromanganese remaining unaffected. However, there are no independently verifiable sources confirming whether beneficiated concentrates or sintered ores qualify as “processed goods,” or whether transition periods or quotas will be established. This will directly determine the form in which Gabonese ores can be exported after 2029.

Tracking Point 3: Power Supply and Railway Infrastructure. Eramet’s memorandum lists access to competitive energy as a prerequisite for its alloy projects; similarly, the capacity of the Trans-Gabon Railway determines whether mines can maintain stable production. If these two elements see no improvement for an extended period, progress on processing projects and current raw ore exports will both be hindered.

Bans are written on paper, but capacity must be built on the ground.

— END —